The Ministry of Public Works, Transport, and Communication (MTPTC) contracted with Estrella, a Dominican construction firm, to undertake the project as part of Haiti’s post-2010 earthquake rebuilding efforts. Following are some key figures about the project scope and budget.
The airport expansion was to cover about 400 acres of land, 160 of which was to be acquired through government expropriation.
Initially estimated to be completed within two years, the new facility would feature a 3,000-meter (9,800-foot) runway and new terminal able to handle 250,000 passengers annually.
The project budget was estimated at about $30 million. According to a Superior Court of Administrative Accounts and Litigation report:
The MTPTC has not responded to a request for comment from The Haitian Times.
The post The Les Cayes airport transformation, by the numbers appeared first on The Haitian Times.